- (A) on all the activities
- (B) on all the activities lying on the critical path
- (C) only on activities lying on the orginal critical path and having flatter cost slopes
- (D) on original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope
Civil Engineering Mcqs
- (A) crash time
- (B) normal time
- (C) optimistic time
- (D) standard time
- (A) minimum
- (B) maximum
- (C) zero
- (D) infinite
- (A) cheapest critical activity
- (B) cheapest non-critical activity
- (C) costliest critical activity
- (D) costliest non-critical activity
- (A) an activity
- (B) an event
- (C) both event and activity
- (D) none of the above
- (A) resources
- (B) project duration time
- (C) both resources and project duration time
- (D) none of the above
- (A) normal durations for all the activities
- (B) crash durations for all activities
- (C) crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities
- (D) crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities
- (A) Drag line
- (B) Hoe
- (C) Clam shell
- (D) Dipper shovel
- (A) Moist loam
- (B) Sand and gravel
- (C) Good common earth
- (D) Wet sticky clay
- (A) Both A and R are true and R is the correct explanation of A
- (B) Both A and R are true but R is not the correct explanation of A
- (C) A is true but R is false
- (D) A is false but R is true