Economic saving of time results by crashing_________________?

Civil Engineering Mcqs

Economic saving of time results by crashing_________________?

(A)  cheapest critical activity

(B)  cheapest non-critical activity

(C)  costliest critical activity

(D)  costliest non-critical activity