Get App on

Play Store

Civil Engineering Mcqs

Crash project duration is obtained by summing the________________?

 (A)  normal durations for all the activities

 (B)  crash durations for all activities

 (C)  crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities

 (D)  crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities

Submitted By :Ali Uppal


Share this... Share on Facebook
Facebook
Tweet about this on Twitter
Twitter
Share on LinkedIn
Linkedin
Share on Whatsapp
Whatsapp

  • IF YOU THINK THAT ABOVE POSTED MCQ IS WRONG.

  • PLEASE COMMENT BELOW WITH CORRECT ANSWER AND ITS DETAIL EXPLANATION.

  • Related Mcqs


    Leave a Reply

    Your email address will not be published. Required fields are marked *