Earliest finish of an activity is always_______________?
  • (A)  greater than earliest event time of the following node
  • (B)  less than earliest event time of the following node
  • (C)  less than or equal to earliest event time of the following node
  • (D)  greater than or equal to earliest event time of the following node
Free float is mainly used to_________________?
  • (A)  identify the activities which can be delayed without affecting the total float of preceding activity
  • (B)  identify the activities, which can be delayed without affecting the total float of succeeding activity
  • (C)  establish priorities
  • (D)  identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities