- (A) Rs. 8,43,750/-
- (B) Rs. 8,75,000/-
- (C) Rs. 10,50,000/-
- (D) Rs. 11,56,250/-
Civil Engineering Mcqs
- (A) normal distribution curve
- (B) Poisson’s distribution curve
- (C) Beta – distribution curve
- (D) none of the above
- (A) greater than earliest event time of the following node
- (B) less than earliest event time of the following node
- (C) less than or equal to earliest event time of the following node
- (D) greater than or equal to earliest event time of the following node
- (A) 2
- (B) 4
- (C) 8
- (D) 7
- (A) 3.5 and 5/6
- (B) 5 and 25/36
- (C) 3.5 and 25/36
- (D) 4 and 5/6
- (A) identify the activities which can be delayed without affecting the total float of preceding activity
- (B) identify the activities, which can be delayed without affecting the total float of succeeding activity
- (C) establish priorities
- (D) identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities
- (A) its latest finish time and earliest start time for its successor activity
- (B) its latest start time and earliest start time
- (C) its latest start time and earliest finish time
- (D) its earliest finish time and earliest start time for its successor activity
- (A) its earliest finish time and earliest start time for its successor activity
- (B) its latest start time and earliest start time
- (C) its latest finish time and earliest start time for its successor activity
- (D) its earliest finish time and latest start time for its successor activity
- (A) preceding activities
- (B) succeeding activities
- (C) the particular activity involved
- (D) none of the above
- (A) 81
- (B) 54
- (C) 36
- (D) 9