- (A) resource levelling
- (B) resource smoothening
- (C) updating
- (D) critical path scheduling
Civil Engineering Mcqs
- (A) decreasing the direct cost and increasing indirect cost
- (B) increasing the direct cost and decreasing the indirect cost
- (C) increasing the direct cost and indirect cost both
- (D) decreasing the direct cost and indirect cost both
- (A) total float
- (B) free float
- (C) interfering float
- (D) independent float
- (A) 15 minutes
- (B) 20.143 minutes
- (C) 21 minutes
- (D) 27 minutes
- (A) is always longest
- (B) is always shortest
- (C) may be longest
- (D) may be shortest
- (A) free float of the activity must be zero but independent float need not be zero
- (B) independent float must be zero but free float need not be zero
- (C) free float and independent float both must be zero
- (D) free float and independent float both need not be zero
- (A) expected time of activity A is greater than the expected time of activity B
- (B) expected time of activity B is greater than the expected time of activity A
- (C) expected time of both activities A and B are same
- (D) none of the above
- (A) greater than or equal to latest event time of preceding node
- (B) less than or equal to latest event time of preceding node
- (C) equal to latest event time of preceding node
- (D) less than latest event time of preceding node
- (A) site located
- (B) foundation is being dug
- (C) the office area is being cleaned
- (D) the invitations are being sent
- (A) 500 cum
- (B) 1000 cum
- (C) 1500 cum
- (D) 2000 cum