The reduction in project time normally results in_______________?
  • (A)  decreasing the direct cost and increasing indirect cost
  • (B)  increasing the direct cost and decreasing the indirect cost
  • (C)  increasing the direct cost and indirect cost both
  • (D)  decreasing the direct cost and indirect cost both
Critical path_____________?
  • (A)  is always longest
  • (B)  is always shortest
  • (C)  may be longest
  • (D)  may be shortest
Whenever an activity has zero total float, then_______________?
  • (A)  free float of the activity must be zero but independent float need not be zero
  • (B)  independent float must be zero but free float need not be zero
  • (C)  free float and independent float both must be zero
  • (D)  free float and independent float both need not be zero
Latest start of an activity is always________________?
  • (A)  greater than or equal to latest event time of preceding node
  • (B)  less than or equal to latest event time of preceding node
  • (C)  equal to latest event time of preceding node
  • (D)  less than latest event time of preceding node