Get App on

Play Store

Civil Engineering Mcqs

Latest start of an activity is always________________?

 (A)  greater than or equal to latest event time of preceding node

 (B)  less than or equal to latest event time of preceding node

 (C)  equal to latest event time of preceding node

 (D)  less than latest event time of preceding node

Submitted By :Ali Uppal


Share this... Share on Facebook
Facebook
Tweet about this on Twitter
Twitter
Share on LinkedIn
Linkedin
Share on Whatsapp
Whatsapp

  • IF YOU THINK THAT ABOVE POSTED MCQ IS WRONG.

  • PLEASE COMMENT BELOW WITH CORRECT ANSWER AND ITS DETAIL EXPLANATION.

  • Related Mcqs


    Leave a Reply

    Your email address will not be published. Required fields are marked *