Get App on

Play Store

Civil Engineering Mcqs

If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then______________?

 (A)  expected time of activity A is greater than the expected time of activity B

 (B)  expected time of activity B is greater than the expected time of activity A

 (C)  expected time of both activities A and B are same

 (D)  none of the above

Submitted By :Ali Uppal


Share this... Share on Facebook
Facebook
Tweet about this on Twitter
Twitter
Share on LinkedIn
Linkedin
Share on Whatsapp
Whatsapp

  • IF YOU THINK THAT ABOVE POSTED MCQ IS WRONG.

  • PLEASE COMMENT BELOW WITH CORRECT ANSWER AND ITS DETAIL EXPLANATION.

  • Related Mcqs


    Leave a Reply

    Your email address will not be published. Required fields are marked *