In PERT analysis, the time estimates of activities and probability of their occurrence follow_______________?

  • (A)  normal distribution curve
  • (B)  Poisson’s distribution curve
  • (C)  Beta – distribution curve
  • (D)  none of the above
Submitted By :Ali Uppal


Earliest finish of an activity is always_______________?

  • (A)  greater than earliest event time of the following node
  • (B)  less than earliest event time of the following node
  • (C)  less than or equal to earliest event time of the following node
  • (D)  greater than or equal to earliest event time of the following node
Submitted By :Ali Uppal


Submitted By :Ali Uppal


Submitted By :Ali Uppal


Free float is mainly used to_________________?

  • (A)  identify the activities which can be delayed without affecting the total float of preceding activity
  • (B)  identify the activities, which can be delayed without affecting the total float of succeeding activity
  • (C)  establish priorities
  • (D)  identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities
Submitted By :Ali Uppal


Total float for any activity is defined as the difference between________________?

  • (A)  its latest finish time and earliest start time for its successor activity
  • (B)  its latest start time and earliest start time
  • (C)  its latest start time and earliest finish time
  • (D)  its earliest finish time and earliest start time for its successor activity
Submitted By :Ali Uppal


Free float for any activity is defined as the difference between__________________?

  • (A)  its earliest finish time and earliest start time for its successor activity
  • (B)  its latest start time and earliest start time
  • (C)  its latest finish time and earliest start time for its successor activity
  • (D)  its earliest finish time and latest start time for its successor activity
Submitted By :Ali Uppal


The independent float affects only_______________?

  • (A)  preceding activities
  • (B)  succeeding activities
  • (C)  the particular activity involved
  • (D)  none of the above