If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively___________________?

Civil Engineering Mcqs

If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively___________________?

(A)  3.5 and 5/6

(B)  5 and 25/36

(C)  3.5 and 25/36

(D)  4 and 5/6