In a PERT chart___________________?
  • (A)  all activities should be numbered
  • (B)  only important activities should be numbered
  • (C)  only critical activities are numbered
  • (D)  only selected activities are numbered
  • (E)  no activity is numbered
Descripancies of bar chart techniques are________________?
  • (A)  consequential effects of lack in one activity on omer
  • (B)  consequential effects of lack in one activity on the finish date
  • (C)  free time available for an activity can’t be predicted
  • (D)  effective monitoring/controlling can’t be done
  • (E)  all of the above
CPMis___________________?
  • (A)  synthesising in concepts
  • (B)  is built of activities oriented program-mes
  • (C)  is, based on one time eytimate
  • (D)  is used for repetitive works
  • (E)  all of the above