Activity s,lack or float of any event on a PERT/CPM chart is represented by__________________?

Mechanical Engineering Mcqs

Activity s,lack or float of any event on a PERT/CPM chart is represented by__________________?

(A)  latest start time of succeeding event -earliest finish time of preceding event activity time

(B)  latest start time of the event – earliest start time of the event

(C)  latest finish time of event – earliest finish time of the event

(D)  anyone of the above

(E)  none of the above