Pick up the correct statement. Dummy activity on a PERT/CPM chart means, it_________________?
(A) consumes time, but no resources
(B) consumes resources but no time
(C) consumes neither time nor resources
(D) is a dangling event
(E) consumes both resources and time
Share this... |
![]() Facebook
|
![]() Twitter
|
![]() Linkedin
|
![]() Whatsapp
|
Your email address will not be published. Required fields are marked *