- (A) a project is divided into various activities
- (B) required time for each activity is established
- (C) sequence of various activities is made according to their importance
- (D) network is drawn by connecting the activities and the events
- (E) all of the above
- (A) high initial investment for the specialized facilities
- (B) skilled labour to operate machines
- (C) production time is longer, requiring more goods in inventory
- (D) high cost of inspection
- (E) costly and complex production control
- (A) the flow of material in the plant
- (B) the methods of proper utilization of manpower
- (C) the methods of proper utilization of machines
- (D) the layout of factory facilities
- (E) normal route of workers through the plant
- (A) is artificially introduced
- (B) is represented by a dotted line
- (C) does not require any time
- (D) all of the above
- (E) none of the above
- (A) event
- (B) float
- (C) duration
- (D) constraint
- (E) none of the above
- (A) normal
- (B) binomial
- (C) beta
- (D) exponential
- (E) Gaussian
- (A) maximum float
- (B) minimum float
- (C) zero float,
- (D) average float
- (E) none of these
- (A) the minimum time required for completion of project
- (B) the maximum time required for completion of project
- (C) maximum cost required for completion of project
- (D) minimum cost required for completion of project
- (E) none of the above
- (A) positive value
- (B) negative value
- (C) zero value
- (D) same value
- (E) none of the above