Crash project duration is obtained by summing the________________?
  • (A)  normal durations for all the activities
  • (B)  crash durations for all activities
  • (C)  crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities
  • (D)  crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities