A milestone chart_______________________?
  • (A)  shows the inter dependences of various jobs
  • (B)  depicts the delay of jobs, if any
  • (C)  points outgoing ahead of schedule of jobs, if any
  • (D)  all of the above
  • (E)  none of the above
The basic difference between PERT and CPM is that_____________?
  • (A)  PERT deals with events and CPM with activities
  • (B)  critical path is determined in PERT only
  • (C)  costs are considered on CPM only and not in PERT
  • (D)  guessed times are used in PERT and evaluated times in CPM
  • (E)  PERT is used in workshops and CPM in plants