For the construction of water bound macadam roads, the correct sequence of operations after spreading coarse aggregates is________________?
  • (A)  dry rolling, wet rolling, application of screening and application of filler
  • (B)  dry rolling, application of filler, wet rolling and application of screening
  • (C)  dry rolling, application of screening, wet rolling and application of filler
  • (D)  dry rolling, application of screening, application of filler and wet rolling