Get App on

Play Store

Civil Engineering Mcqs

For the construction of water bound macadam roads, the correct sequence of operations after spreading coarse aggregates is________________?

 (A)  dry rolling, wet rolling, application of screening and application of filler

 (B)  dry rolling, application of filler, wet rolling and application of screening

 (C)  dry rolling, application of screening, wet rolling and application of filler

 (D)  dry rolling, application of screening, application of filler and wet rolling

Submitted By :Ali Uppal


Share this... Share on Facebook
Facebook
Tweet about this on Twitter
Twitter
Share on LinkedIn
Linkedin
Share on Whatsapp
Whatsapp

  • IF YOU THINK THAT ABOVE POSTED MCQ IS WRONG.

  • PLEASE COMMENT BELOW WITH CORRECT ANSWER AND ITS DETAIL EXPLANATION.

  • Related Mcqs


    Leave a Reply

    Your email address will not be published. Required fields are marked *