The area under the Beta – distribution curve is divided into two equal parts by_______________?

  • (A)  most likely time
  • (B)  optimistic time
  • (C)  pessimistic time
  • (D)  expected time
Submitted By :Ali Uppal


Which of the following is not a PERT event ?

  • (A)  site investigation started
  • (B)  sessional work completed
  • (C)  bus starts from Jaipur
  • (D)  class is being attended
Submitted By :Ali Uppal


Which of the following is a weakness of bar chart ?

  • (A)  interdependencies of activities
  • (B)  project progress
  • (C)  uncertainties
  • (D)  all of the above
Submitted By :Ali Uppal


Submitted By :Ali Uppal


The permissible bending stresses Pbet for steel slab bases should not exceed_______________?

  • (A)  1500 kg/cm2
  • (B)  1650 kg/cm2
  • (C)  1800 kg/cm2
  • (D)  1890 kg/cm2
Submitted By :Ali Uppal


All reinforcement should be free from_________________?

  • (A)  paints
  • (B)  loose rust
  • (C)  loose mill scales
  • (D)  All the above
Submitted By :Ali Uppal


Submitted By :Ali Uppal


Removal of props under______________?

  • (A)  slabs spanning upto 4.5 m is 14 days
  • (B)  beams spanning upto 6 m is 14 days
  • (C)  slabs spanning upto 4.5 m is 7 days
  • (D)  All the above
Submitted By :Ali Uppal


Submitted By :Ali Uppal


Submitted By :Ali Uppal