- (A) material handling
- (B) reducing the waiting time or idle Jajme
- (C) better utilization of man services
- (D) effective use of machines
- (E) none of the above.
Mechanical Engineering Mcqs
- (A) Jeck Gilberth
- (B) Gnatt
- (C) Taylor
- (D) Newton
- (E) none of the above
- (A) functional organisation
- (B) line organisation
- (C) staff organisation
- (D) line and staff organisations
- (E) scalar organisation
- (A) inflated system
- (B) primary cost method
- (C) current value method
- (D) fixed price method
- (E) variable price method
- (A) forecasting sales
- (B) production schedule
- (C) scheduling and routing
- (D) linear programming
- (E) none of the above
- (A) break even point analysis
- (B) production schedule
- (C) material handling layout
- (D) determining selling price
- (E) value analysis
- (A) optimum lot size
- (B) highest level of inventory
- (C) lot corresponding to break-even point
- (D) capability of a plant to produce
- (E) none of the above
- (A) management
- (B) labour court
- (C) high court/supreme court
- (D) board of directors
- (E) president
- (A) all industries
- (B) all process industries and thermal power plants
- (C) only major industries
- (D) only key industries
- (E) all industries employing more than 100 workers
- (A) detailed calculations
- (B) convenience
- (C) table of random numbers
- (D) past experience
- (E) fixed percentage of daily production