Which of the following is a systematic attempt to specify threats to the project plan ?

Software Engineering Mcqs

Which of the following is a systematic attempt to specify threats to the project plan ?

(A)  Risk identification

(B)  Performance risk

(C)  Support risk

(D)  Risk projection