Which of the following does not apply to agility to a software process ?

Software Engineering Mcqs

Which of the following does not apply to agility to a software process ?

(A)  Uses incremental product delivery strategy

(B)  Only essential work products are produced

(C)  Eliminate the use of project planning and testing

(D)  All of the mentioned