Arrange the following activities for making a software product using 4GT. i. Design strategy ii. Transformation into product iii. Implementation iv. Requirement gathering ?

Software Engineering Mcqs

Arrange the following activities for making a software product using 4GT. i. Design strategy ii. Transformation into product iii. Implementation iv. Requirement gathering ?

(A)  1, 4, 3, 2

(B)  4, 3, 1, 2

(C)  4, 1, 3, 2

(D)  1, 3, 4, 2