The time by which the activity completion time can be delayed without affecting the start of succeeding activities, is Known as_________________?
(A) duration
(B) total float
(C) free float
(D) interfering float
(E) none of the above
The time by which the activity completion time can be delayed without affecting the start of succeeding activities, is Known as_________________?
(A) duration
(B) total float
(C) free float
(D) interfering float
(E) none of the above