(A) the maximum time which an activity might require
(B) the average time required for a job
(C) the most probable time considering all conditions
(D) the minimum time in which an activity can possibly be accomplished
(E) the earliest finish
(A) the maximum time which an activity might require
(B) the average time required for a job
(C) the most probable time considering all conditions
(D) the minimum time in which an activity can possibly be accomplished
(E) the earliest finish