If E is the duration, ES and EF are die earliest start and finish times, LS and LF are latest start and finish times, then the following relation holds good______________________?

Mechanical Engineering Mcqs

If E is the duration, ES and EF are die earliest start and finish times, LS and LF are latest start and finish times, then the following relation holds good______________________?

(A)  EF=ES+D

(B)  LS=LF-D

(C)  LF = LS + D

(D)  D = EF-ES

(E)  all of the above