The net head under which the turbine reaches its peak efficiency at synchronous speed is called________________?

Civil Engineering Mcqs

The net head under which the turbine reaches its peak efficiency at synchronous speed is called________________?

(A)  design head

(B)  rated head

(C)  gross head

(D)  operating head