The expected out turn of cement concrete 1 : 2 : 4 per mason per day is_________________?

Civil Engineering Mcqs

The expected out turn of cement concrete 1 : 2 : 4 per mason per day is_________________?

(A)  1.5 m 3

(B)  2.5 m3

(C)  3.5 m3

(D)  5.0 m3