The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is ________________?

Civil Engineering Mcqs

The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is ________________?

(A)  1.00 m3

(B)  1.25 m3

(C)  1.50 m3

(D)  1.75 m3