The density of population over 40 hectares is 250/hectare. If water supply demand per day is 200 litres and sewage discharge is 80% of water supply, the sewage flow in sewers of separate system, is_____________________?

Civil Engineering Mcqs

The density of population over 40 hectares is 250/hectare. If water supply demand per day is 200 litres and sewage discharge is 80% of water supply, the sewage flow in sewers of separate system, is_____________________?

(A)  0.05552 cumec

(B)  0.05554 cumec

(C)  0.05556 cumec

(D)  0.0556 cumec