In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having________________?

Civil Engineering Mcqs

In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having________________?

(A)  longest duration

(B)  highest cost slope

(C)  least cost slope

(D)  shortest duration