In “full face” method of constructing tunnels, the first operation relates to______________?

Civil Engineering Mcqs

In “full face” method of constructing tunnels, the first operation relates to______________?

(A)  removal of bottom portion

(B)  excavation of one drift in the centre

(C)  removal of top portion

(D)  excavation being done along the periphery