If the risk of a flood occurring in the next 10 years is accepted to 10%, then the return period for design should be__________________?

Civil Engineering Mcqs

If the risk of a flood occurring in the next 10 years is accepted to 10%, then the return period for design should be__________________?

(A)  1 + (0.9)010

(B)  1 – (0.9)°l0

(C)  1/(1-0.9°10)

(D)  1/(1+ 0.9010)