If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be__________________?

Civil Engineering Mcqs

If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be__________________?

(A)  2.3% and 84.1%

(B)  97.7% and 84.1%

(C)  97.7 % and 15.9%

(D)  15.9% and 97.7%