A manufacturing firm maintains one product assembly line to produce signal generators. Weekly demand for the generators is 35 units. The line operates for 7 hours per day, 5 days per week. What is the maximum production time per unit in hours required of the line to meet the demand ?

Civil Engineering Mcqs

A manufacturing firm maintains one product assembly line to produce signal generators. Weekly demand for the generators is 35 units. The line operates for 7 hours per day, 5 days per week. What is the maximum production time per unit in hours required of the line to meet the demand ?

(A)  1.0 hour per unit

(B)  1.2 hours per unit

(C)  1.4 hours per unit

(D)  1.6 hours per unit



Share this... Share on Facebook
Facebook
Tweet about this on Twitter
Twitter
Share on LinkedIn
Linkedin
Share on Whatsapp
Whatsapp

  • IF YOU THINK THAT ABOVE POSTED MCQ IS WRONG.

  • PLEASE COMMENT BELOW WITH CORRECT ANSWER AND ITS DETAIL EXPLANATION.

  • Related Mcqs


    Leave a Reply

    Your email address will not be published. Required fields are marked *