It takes 6 hours to dry a wet solid from 50% moisture content to the critical moisture content of 15%. How much longer it will take to dry the solid to 10% moisture content, under the same drying conditions? (The equilibrium moisture content of the solid is 5%) ?

Chemical Engineering Mcqs

It takes 6 hours to dry a wet solid from 50% moisture content to the critical moisture content of 15%. How much longer it will take to dry the solid to 10% moisture content, under the same drying conditions? (The equilibrium moisture content of the solid is 5%) ?

(A)  15 min

(B)  51 min

(C)  71 min

(D)  94 min